Electronic IndustriesmainNew Technologies

97- Construction of the first Francis horizontal hydroelectric turbine in Iran

For the first time, the Francis Horizontal hydroelectric turbine was designed and built entirely by local engineers at the 10 MW free dam power plant.

Prior to this, in all the plans for the construction of hydropower power plants, foreign company specialists were used to design the turbine, and part of the turbine designed in Iran and most of these parts were manufactured abroad and imported into Iran.

The Francis horizontal hydroelectric turbine generates 3.3 MW.
three 3.3 MW turbines produce electricity at the same time in 10 MW Free Power Plant and The country’s electricity generation capacity has increased by 10 MW.